Bishkek Water-supply and Wastewater Rehabilitation Project – Phase II: Development of detailed design of sewerage collector with a length of 11 km in Bishkek.

Prepare to print

Bishkek Water-supply and Wastewater Rehabilitation Project – Phase II: Development of detailed design of sewerage collector with a length of 11 km in Bishkek.

Financed organization: European Bank for Reconstruction and Development (EBRD)

 

Outputs

  • Topographic, geological and hydrogeological surveys
  • Detailed design of the new sewerage collector, the detailed design for the renovation and extension of the receiving chamber and the detailed design for the extension of the inlet chamber of the WWTP
  • Computer modelling, simulations
  • Bill of quantities, technical specifications, arrangement of construction project (POS)
  • Environmental impact assessment
  • Author’s Supervision